High Rise Building Schedule

Muhammad Zeeshan KhanMember for 18 years 7 months
Created
10
3
0

hi there 

is there any one share some of his best experience for high rise building project schedule any pdf or XER will really help 

or can you please give list of activities for one typical floor with or without duration 

you can send me the info as email on tumharabina@yahoo.com

thanks in Advanced 

M 

10 replies

Oldest first
  1. 0
    Muhammad Zeeshan Khan ·

    no reply yet !!!!!!

    no reply yet !!!!!! 

  2. 0
    Raymund de Laza ·

    Hi,There are high rise

    Hi,

    There are high rise building such as Water Tank Tower with a revolving Restaurant on Top, Guard House Tower Building around a perimeter fence of a Military Compound, Tower buildings such as in Dubai.

    The list of activities depends on what is required by the Contract Project.

     

    Regards,

     

     

  3. 0
    Gary Whitehead ·

    Muhammad, Most people on this

    Muhammad,

     

    Most people on this forum don't share their programmes.

    I personally never do, because I feel the programmes I create are the property of my client, and not mine to share.

    Other people never do becuase they feel it is giving away their experience for free, when they normally charge for it.

    Others don't because they feel it is helping someone who doesn't know how to do their job to stay in a job which they don't deserve.

    Some people do share their work but not many, so don't be annoyed or suprised if you don't get what you are looking for.

  4. 0
    Muhammad Zeeshan Khan ·

    Well i am looking for simple

    Well i am looking for simple high rise building used as an office upto 20th floor have a curtain wall .

    I need some list of Mechanical, Electrical and Plumbing activities 

  5. 0
    Muhammad Zeeshan Khan ·

    Gary its a shame that people

    Gary its a shame that people dont help each other i am not ask for the programme i am just asking for the list of activities 

    List of activities does not belongs to any programme and it is always good to share your experience and best practices you have used.

    Those who not share are mostly P6 jockey and I appreciate and salute all those project professional who are helping planning community without thinking about doesn't know how to do their job to stay in a job which they don't deserve,feel it is giving away their experience for free" they all are mean little buggers and they should not be on this forum 

    Cheers

  6. 0
    John Peter ·

    Muhammad you are absolutely

    Muhammad you are absolutely right this forum is made to help all planners in our community.

    People like Gary don’t understand this. Most of the planners  who write that sort of comments spend most of their office time on internet and rest of the time doing some design plans for desktop surveys.

     If you don’t have any knowledge how do you share something!!! But can give loads of lame excuses.

    I hope this example help you. Most people in this forum share their experience because they have knowledge

     

    Activity NameOriginal DurationRemaining DurationStartFinishTotal Float
    City Center Office Building Addition68155401-Nov-10 A3-Jul-130
      Design and Engineering107001-Nov-10 A06-Apr-11 A 
        Design Building Addition55001-Nov-10 A19-Jan-11 A 
        Start Office Building Addition Project0001-Nov-10 A  
        Review and Approve Designs22017-Jan-11 A17-Feb-11 A 
        Assemble Technical Data for Heat Pump7016-Feb-11 A25-Feb-11 A 
        Review Technical Data on Heat Pumps27024-Feb-11 A06-Apr-11 A 
      Foundation1469823-Feb-11 A19-Sep-11175
        Begin Building Construction0028-Feb-11 A  
        Site Preparation43023-Feb-11 A18-Apr-11 A 
        Excavation24242-May-116-Jun-11127
        Install Underground Water Lines12123-Jun-1121-Jun-11127
        Install Underground Electric Conduit12123-Jun-1121-Jun-11127
        Form/Pour Concrete Footings242421-Jun-1126-Jul-11127
        Concrete Foundation Walls242425-Jul-1126-Aug-11127
        Form and Pour Slab121226-Aug-1114-Sep-11127
        Backfill and Compact Walls5513-Sep-1119-Sep-11127
        Foundation Phase Complete00 19-Sep-11178
      Structure15115119-Sep-1120-Apr-12306
        Erect Structural Frame484819-Sep-1125-Nov-11127
        Begin Structural Phase0025-Nov-11 418
        Floor Decking343425-Nov-1113-Jan-12127
        Concrete First Floor363611-Jan-121-Mar-12127
        Erect Stairwell and Elevator Walls24241-Mar-124-Apr-12139
        Concrete Basement Slab24241-Mar-124-Apr-12139
        Concrete Second Floor36361-Mar-1220-Apr-12127
        Structure Complete00 20-Apr-12127
      Mechanical/Electrical Systems56254914-Apr-11 A26-Jun-130
        Rough-In Phase Begins0012-Mar-12 234
        Rough In Complete00 5-Feb-130
        Elevator2182184-Apr-1212-Feb-1390
          Install Elevator Rails and Equipment334-Apr-126-Apr-12217
          Install Elevator Cab and Finishes555-Feb-1312-Feb-1391
        HVAC56254914-Apr-11 A26-Jun-130
          Prepare and Solicit Bids for Heat Pump15214-Apr-11 A4-May-110
          Review Bids for Heat Pump10104-May-1117-May-110
          Award Contract for Heat Pump6617-May-1125-May-110
          Fabricate and Deliver Heat Pump and Controls42242225-May-1123-Jan-130
          Install HVAC Ducts242412-Mar-1213-Apr-12186
          Insulate Ducts5518-Jun-1225-Jun-12140
          Set Heat Pump12124-Jan-1322-Jan-130
          Relocate HVAC Chiller7722-Jan-131-Feb-130
          Startup and Test HVAC221-Feb-135-Feb-130
          Install AC Grills and Registers558-Apr-1315-Apr-1323
          Test and Balance HVAC Equipment2221-Jun-1326-Jun-130
        Plumbing and Electrical25825820-Jan-1223-Jan-136
          Set Mechanical and Electrical Equipment363620-Jan-1212-Mar-12186
          Rough-In Plumbing/Piping3324-Aug-1229-Aug-1272
          Install Wiring and Cable363631-Aug-1223-Oct-1272
          Connect Equipment1122-Jan-1323-Jan-136
      Exterior Finishes33628917-Feb-11 A19-Jun-12266
        Close-In Phase Begins0015-May-12 296
        Building Enclosed00 18-Jun-12127
        Brick31226517-Feb-11 A15-May-12124
          Assemble Brick Samples0017-Feb-11 A  
          Review and Approve Brick Samples30028-Feb-11 A13-Apr-11 A 
          Prepare and Solicit Bids for Brick Exterior15018-Mar-11 A13-Apr-11 A 
          Review Bids for Brick15008-Apr-11 A28-Apr-11 A 
          Award Contract for Brick5421-Apr-11 A5-May-11377
          Deliver Brick115-May-116-May-11377
          Brick Exterior Walls171720-Apr-1215-May-12127
        Roof242415-May-1219-Jun-12124
          Insulation and Built-up Roofing242415-May-1219-Jun-12127
        Doors and Windows7727-Apr-128-May-12152
          Install Door and Window Frames3327-Apr-121-May-12156
          Install Exterior Doors and Windows551-May-128-May-12156
      Interior Finishes60155425-Feb-11 A3-Jul-130
        Drywall in Offices36365-Feb-1327-Mar-130
        Touch-up and Clean-up2219-Jun-1324-Jun-130
        Finishes Complete00 26-Jun-130
        Punch List5526-Jun-133-Jul-130
        Building Addition Complete00 3-Jul-130
        Plumbing and Lighting Fixtures44448-Apr-1310-Jun-137
          Install Lighting Fixtures778-Apr-1317-Apr-1321
          Install Plumbing Fixtures553-Jun-1310-Jun-137
        Floor and Carpeting58153425-Feb-11 A4-Jun-130
          Assemble and Submit Flooring Samples0025-Feb-11 A  
          Review and Approve Flooring28025-Feb-11 A11-Apr-11 A 
          Prepare and Solicit Bids for Flooring24504-Apr-11 A6-May-11231
          Review Bids for Flooring15156-May-1127-May-11231
          Award Contract for Flooring5527-May-116-Jun-11231
          Fabricate and Deliver Flooring2792793-Jun-116-Jul-12231
          Install Floor and Carpeting121216-May-134-Jun-130
        Carpentry595927-Mar-1319-Jun-130
          Install Ceiling Grid363627-Mar-1316-May-130
          Finish Carpentry and Millwork12123-Jun-1319-Jun-130
        Paint121214-Feb-134-Mar-1376
          Paint Building Interior121214-Feb-134-Mar-1377
  7. 0
    Raymund de Laza ·

    Activity NameOriginal

     Activity NameOriginal Duration
      Design and Engineering51
     Design Building Addition23
     Design43
     Review and Approve Designs9
     Assemble Technical Data for Heat Pump3
     Review Technical Data on Heat Pumps8
      Procurement132
     Prepare and Solicit Bids for Heat Pump10
     Review Bids10
     Prepare and Solicit Bids for Flooring5
     Review Bids for Heat Pump2
     Review Bids for Flooring3
     Award Contract for Heat Pump10
     Review Bids for Brick3
     Award Contract for Flooring1
     Award Contract for Brick2
     Fabricate and Deliver Flooring58
     Deliver Brick58
     Fabricate and Deliver Heat Pump and Controls88
      Sitework 114
     Site work I50
     Sitework95
     Site work II45
      Foundation79
     Foundation64
        Excavation24
     Begin Building Construction0
     Excavation10
        Form Work12
     Install Underground Water Lines5
     Install Storm water lines10
        Concrete79
     Site Preparation10
     Form/Pour Concrete Footings10
     Concrete Foundation Walls14
     Form and Pour Slab10
     Backfill and Compact Walls5
     Foundation Phase Complete0
      Structure 172
     Structure143
     Erect Structural Frame40
     Begin Structural Phase0
     Floor Decking28
     Concrete First Floor60
     Erect Stairwell and Elevator Walls10
     Concrete Basement Slab15
     Concrete Second Floor15
      Mechanical/Electrical Systems133
     Rough-In Phase Begins0
     Rough In Complete0
      Elevator 165
     Elevator138
     Install Elevator Rails and Equipment40
     Install Elevator Cab and Finishes20
      Plumbing and Electrical181
     Set Mechanical and Electrical Equipment15
     Electrical Costs152
     Rough-In Plumbing/Piping45
     Install Wiring and Cable45
     Connect Equipment3
      HVAC 186
     HVAC, Plumbing & Fire Protection155
     Install HVAC Ducts25
     Insulate Ducts2
     Set Heat Pump5
     Relocate HVAC Chiller3
     Startup and Test HVAC1
     Install AC Grills and Registers5
     Test and Balance HVAC Equipment1
      Exterior Finishes278
     Exterior Finish Costs205
        Brick 266
     Assemble Brick Samples3
     Review and Approve Brick Samples10
     Brick Exterior Walls14
        Roof 10
     Insulation and Built-up Roofing10
        Doors and Windows3
     Install Door and Window Frames1
     Install Exterior Doors and Windows2
      Interior Finishes373
     Drywall in Offices15
     Interior Finish Costs44
     Finishes Phase Begins0
     Finishes Milestone0
     Touch-up and Clean-up1
     Building Addition Complete0
     Punch List2
        Plumbing and Lighting Fixtures17
     Install Lighting Fixtures3
     Install Plumbing Fixtures2
        Floor and Carpeting362
     Assemble and Submit Flooring Samples8
     Review and Approve Flooring10
     Install Floor and Carpeting5
        Carpentry30
     Install Ceiling Grid15
     Finish Carpentry and Millwork5
        Paint 36
     Paint Building Interior30
  8. 0
    Muhammad Zeeshan Khan ·

    My gratitude knows no bounds

    My gratitude knows no bounds to all those who help me 

  9. 0
    Masyitah Sunbae ·

    hye...anyone can help me..i

    hye...anyone can help me..i need example activity shedulling that high rise building such condominium or apartment in 4 block and duration 3 year...please help me..

  10. 0
    Zoltan Palffy ·

    even easierfoundations1st

    even easier

    foundations

    1st floor 

    2nd floor repeat copy cut paste

Log in or join to reply