Cash flow distribution in P6

Osama HaggagMember for 12 years 8 months
Created
3
2
0

I need to change the way that P6 distribute the budget cost.Its distribute the cost for each work hour ,for example if I have one activity start on 10 Apr.14 and finish on 10.May.14 the P6 will devide the cost of the activity to two parts , one in april and one in may according to the units ( the work hours ).

but I need to make the P6 respect the start or finish dates.,to put the total cost of the activity in one month .

there is some way ?

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Use the Ordinal Date in the

    Use the Ordinal Date in the Timescale....

  2. 0
    Osama Haggag ·

    I think taht you didint got

    I think taht you didint got my point,what i need is to put all money for same activity in one month not devide according to days,If the activity start on Jan an finish in Feb , I need to assighn all budget cost in Jan,no to make part in Jan and part in Feb

  3. 0
    Raymund de Laza ·

    Yes, absolutely I did not get

    Yes, absolutely I did not get your point.

    In my understanding now, you want the Assignment to be eitheir on the Fist Day or at the End of the activity Duration.

    I suggests Make use of the Resource Curve.