Why At completion Total Cost differes from Budgeted Totat Cost
In the Open Standard
Fareed MemonMember for 12 years 4 months
- Created
- 0
- 4
0
Hello every one,
I have cost loaded baseline plan and also have an updated baseline plan.
I have noticed that if a task is 100% completed its
AT COMPLETION TOTAL COST value
becomes "0"
where as my client is asking me that value of
Budgeted Total Cost should be equal to At completion Total Cost.
Can any one please let me know where I am lacking and what will be the solution.
Thanks for your time.
Regards
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?