Rules of credit - drawings
In the Open Standard
Dennis HanksMember for 19 years 6 months
- Created
- 4
- 3
0
Is there general agreement on the rules of credit for drawing development? I'm using: Start 10%, Check 70%, Approve 90%, Issue 100%. Any thoughts appreciated.
Please note what industry the rules apply. The above rules came from an Oil and Gas client. Thanks.