Skip to content

MEP Sequence

Project PlannerMember for 12 years 6 months
Created
3
1
0

I need the sequence of work and relationship for the following Electrical activities

Embedded Conduiting in the Floor Slab
Conduiting in Blockworks
Installation of Trunking
Install Cable Tray
Wiring for Lighting
Wiring for Power
Wiring for Fire Alarm
Wiring for Emergency Lighting System
Dressing & Termination of Fire Alarm
Wiring for IP CCTV
Dressing & Termination of Emergency Lighting
Wiring for SMATV System
Dressing & Termination of SMATV
Wiring for Structured Cabling
Wirng for BMS
Dressing & Termination of Structured Cabling
Dressing & Termination of BMS
Dressing & Termination of CCTV
Uninteruptable Power Supply (UPS)
Central Battery System
Installation of BMS

Thanks in advance

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi ProjectThat is too much

    Hi Project

    That is too much detail.

    You need to split the MEP into 3 tasks - Ducting > Pipework> Containment.

    These are place vertically in risers and horizontally in ceiling zones and / or floor zones.

    Cables are placed in the containment after weather tight conditions.

    IT cables have seperate containment and must not be placed close to HV / LV cables.

    Best regards

    Mike Testro

  2. 0
    Zoltan Palffy ·

    conduit, wire then

    conduit, wire then terminations

    in slab would be first

    then the highest component in the ceiling 

    then any in-wall work 

  3. 0
    Zoltan Palffy ·

    conduit, wire then

    conduit, wire then terminations

    in slab would be first

    then the highest component in the ceiling 

    then any in-wall work 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?