Car sale showroom - split foundation and Steel structure

Engy SarhanMember for 11 years 11 months
Created
3
3
0

Hi there,

 

I am wondering if anyone could help me with a sequence and possible durations to put together a schedule for a carsale showroom, it should have a split foundation and a steel structure superstruction, single story building with an area of 3000 sqm.

Any help will be appreciated.

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    optain all permitsidentify

    optain all permits

    identify any existing utilities

    relocate and existing utilities

    rough grade site 

    install underground utilities conduit ductbanks etc

    form, rebar, pour slab on grade

    Erect steel structure

    install building skin

    install roofing

    interior finishes

    look at RS Means or similar estimating software and books for durations based on quantity and or square footage

     

     

  2. 0
    Mike Testro ·

    Hi ZoltanA comprehensive

    Hi Zoltan

    A comprehensive list.

    What about design and lead times for procurement.

    Sometimes it is quicker to get the steel up and then do the slab.

    Best regards

    Mike Testro

  3. 0
    Zoltan Palffy ·

    yes you can put the steel up

    yes you can put the steel up and then do the slab depending on what the columns sit on. This will obviously hold off all trades until the steel is set since no one can be working under the steel while it is going up. 

    It is harder to do underground in the slab area AFTER the steel is up due to the columns being in the way.

    I would look at the geographical location of the project and look at the time of year that the roof planned to go in then consider the weather conditions and decide if it is bestto get the projetc under roof ASAP.

     

    As far as the design you wil have

    civil or Undergound and site design

    structural 

    electrical 

    mechanical 

    architectural 

    lead times will be for your steel and glazing of the large panes of glass

     

     

     

Log in or join to reply