Constrains report

Andrew FamMember for 12 years
Created
4
2
0

How to make a report to know which activities has a constrain in the whole program ??

4 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi Andrew.In the global

    Hi Andrew.

    In the global fiters you have filter for the constraints.

    Regards Johannes

  2. 0
    Raymund de Laza ·

    Andrew...It is also available

    Andrew...

    It is also available in Schedule... View Log....

  3. 0
    Zoltan Palffy ·

    if you are using P6 run a

    if you are using P6 run a filter

    where primary constraint is not equal to (leave this blank)

    this will give you everything with a constraint on it

  4. 0
    Andrew Fam ·

    Thanks alot

    Thanks alot 