Approval for Revision Programme
- Created
- 6
- 2
Dear All,
Please provide your comments regarding this matter.
We have given approval for the Baseline programme & after that there was a 2 months delay had occurded due to a Employers delay event but contractor did not claim any EOT (Not submitted any EOT notices up to now & issue was closed now). Now, they have submitted revised programme as per Client request & they are claming 2 months EOT in the programme but with out supporting the EOT event.
If we grant the approval for the Programme, is that mean "Contractor Entilte for the 2 Months EOT"
Thank You
Prageeth
6 replies