Progress update of out of sequence activities

Sunil BabuMember for 15 years 11 months
Created
6
2
0

Dear All,

What will be the effect of  updating an out of sequnce activity in a Baseline programme (Cost loaded) in a Villa Project.

Planned dates of that activity falls in the month of May, but actvity completed in the schedule period. (Schedule % is 0, Activity % is 100).

How will it affect the Performance %  ?. Settings for EV calculations are as follows.

1. Performance % equal to Activity %

2. ETC is equal to remaining cost.

3. Budgeted values with current dates.

4. Progress override

Best Regards,

Sunil.

6 replies

Oldest first
  1. 0
    Sunil Babu ·

    Dear Experts,After updating

    Dear Experts,

    After updating the Baseline , Actual budget cost of  many of the activities  not displaying.( Activities which are having schedule percentage - 0% but activity percentage -100%) . Why it is happening.? Actualy those activities 100% completed during the schedule period.

    This is affecting the EV calculations.

    Your reply will be highly appreciable.

    Beast Regards,

    Sunil.

     

  2. 0
    Zoltan Palffy ·

    are you putting an actual

    are you putting an actual start and an actual fnish DATES on the activities ?

     

    what type of percent complete are you using ?

  3. 0
    Sunil Babu ·

    Zoltan,Already updated with

    Zoltan,

    Already updated with actual start and actual finish.

    Using percentage complete type - Duration percentage

    Regards,

    Sunil.

  4. 0
    Zoltan Palffy ·

    the budgeted units wil be

    the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab. 

    The actual cost have to be updated manually but the units wil be updated 

  5. 0
    Zoltan Palffy ·

    the budgeted units wil be

    the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab. 

    The actual cost have to be updated manually but the units wil be updated 

  6. 0
    Sunil Babu ·

    Zoltan,Thank you, I have

    Zoltan,

    Thank you, I have added the actual cost manually.

    Best Regards,

    Sunil

Log in or join to reply