Adverse Weather
In the Open Standard
Johan VerhoevenMember for 14 years 9 months
- Created
- 6
- 4
0
hello,
I need to build a schedule including adverse weather based on Q50 and one Q90. What does it exactly mean?
Second part of the question each affected activity shall show networking time and adverse weather delays? How can this be done? I assume it should be seen in the gantt chart but one activity should show both i.e. net working time and adverse weather.
Can this be done in PRIMAVERA P6 alternatively in MS PROJECT? Dan if positive anwser i would be very interested in finding out how.
Thank in advance,
johan