Dear All,

For the Activity schedule and the resource loading is it required to included the hours or percentage for the weather factor.

Regards

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    https://www.linkedin.com/puls

    https://www.linkedin.com/pulse/new-aace-recommended-practice-adverse-weather-chris?loadAction=comment&midToken=AQEz4oanWrwHzw&trk=eml-mention-reply-mp-cmt&fromEmail=fromEmail&ut=0CNk2nPRIffCY1 

    http://www.aacei.org/toc/toc_84R-13.pdf

    Good Luck

  2. 0
    Zoltan Palffy ·

    that depends on the

    that depends on the specifications but regardless I would certainly include both.

    I would create an anticipated adverse weather in my calendar and assign my exterior work activities to this calendar.

    I would also add resource to my schedule so that you can track the required budgeted manpower as well as the actual manpower on the project. 