Skip to content

Adding resource man hours to a schedule

Alan BanksMember for 15 years 7 months
Created
0
1
0

Should resource man hours that are added into a schedule contain an inefficiency factor or be solelyestimated direct hours to complete a task? There's one school of thought that the resultant resource histogram should show the additional resourcing required due to "possible" inefficiencies whereas a different school of thought says the histogram should be based on only activity direct hours and not to include an inefficiency factor. 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?