Remaining Units are not calculated correctly in Primavera P6

Mahmoud AzabMember for 11 years 6 months
Created
1
2
0

When updating a Baseline project and giving an actual start to a task dependant activity , the sum of remaining units and actual units is not equal to the budgeted units.

Any ideas why this happens?

1 reply

Oldest first
  1. 0
    Ssp Ssp ·

    check the duration type of

    check the duration type of activity. is it fixed units?

    After updating the progress, if there is any differnce in at complete and original duration, and duration type is fixed units/time, the sum of remaining units and actual units will not be equal to budgeted units.