Hi all,

I need help on P6 scheduling. I have a project which starts on Dec. 2015 and after inserting the activities I press F9 and selecting data date which is in Dec. 2015, the activity is registred as having started as I see on the activity information that the start box is checked and the activity bar has changed. My question, why would the F9 (scheduling) make the project to start when the date is a future date?

You comments are appreciated.

4 replies

Oldest first
  1. 0
    Rafael Davila ·

    http://www.cpmsolutions.ca/au

    http://www.cpmsolutions.ca/auto-compute-actuals-vs-update-progress/

  2. 0
    Zoltan Palffy ·

    pressing F9 would would NEVER

    pressing F9 would would NEVER make the activity have an actual start date unless you check the actual start box or unless you 

    select  “Apply Actuals: from the tools selection.

  3. 0
    Anthony Obasi ·

    Thanks Zolton for that

    Thanks Zolton for that reassuring and confident manner in noting pressing F9 will not work this way. I will have to check if soemthing is wrong somewhere.

    Thank you.

  4. 0
    Arslan Shahid ·

    Dear Anthony Obasi, IT IS

    Dear Anthony Obasi,

     

    IT IS IMPOSSIBLE THAT PRESSING F9, ADDS ACTUALS TO THE PROJECT.

    You must be using " APPLY ACTUALS"

     

    You need to play around Calenders to see if it causes any abnormality.

     

    Regards,

    “For more queries, you can always contact me here or in person:ce.arslanshahid@gmail.com”

    Arslan Shahid