14 day rolling calendar

Ian McDonaldMember for 11 years 2 months
Created
2
2
0

Hi

Does anyone know how to set a 14 day rolling calendar in P6.

Im trying to make it 11 days working 3 days non working.

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you will have to do this

    you will have to do this manually since it changes every 2 weeks 

  2. 0
    Rafael Davila ·

    There should be a way to

    There should be a way to model recurring period, rolling calendars are not uncommon.

    RollingCalendar photo RollingCalendar_zpsvwh88rol.jpg

Log in or join to reply