Claim delay submission

Moh HamMember for 15 years 7 months
Created
3
2
0

Can anybody advice if there is any code or standard mention the  contain of the claim submission by the contractor, and can I instruct the contractor as an engineer for the project to use a specified way of analyzing the claim such as window analysis for example.

Thank you

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I think you need to first

    I think you need to first look at what your scheduling specifcation says in that regard. If it is silent you can certainly recommend an analysis type and point out the pros and cons of using this type of analysis 

  2. 0
    Mike Testro ·

    Hi MohIf you are receiving a

    Hi Moh

    If you are receiving a delay claim for review it is best to wait until the submission arrives and then make comments.

    If you try to restrict the claimant's methods it will work against you if it goes to a dispute tribunal.

    In any case I would never suggest a Windows analysis.

    Best regards

    Mike Testro

  3. 0
    Patrick Weaver ·

    There are multiple methods of

    There are multiple methods of claiming and assessing delays. Restricting options is unlikely to be helpful.  For a brief summary of the options offered by AACEi and the 'Delay & Disruption Protocol' see: http://www.mosaicprojects.com.au/Resources_Papers_035.html 