Hi,

Can someone suggest me, wheather S curved generated from Manpower Loading & S Curve generated from Cost loading be the same.

If I keep the weightage of cost and adjust the manpower based on that cost weighted percentage. Will that be right ????

 

Please advise.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    I doubt that they will ever

    I doubt that they will ever be the same since you would include procurement of equipment as a dollar item not necessarily any direct labor manhours are associated with this.

    no you can't do that you might have a piece of equipment that costs 1 million dollars but it only takes 1 day to set it. You cant adjust the manpower based on the piece of that equipment that will not work. 