Progress percentage and scope of work
In the Open Standard
Sunil BabuMember for 15 years 11 months
- Created
- 3
- 3
0
Dear All,
The case scenario of the Project is like this :
After completion of gradeslab client removed the scope of the building and given to another contractor.
My question is Option A: Upto that instance can we put the remaining works of that building as 100% complete, or option B we have to revise the Baseline by removing the remaining activities of that Building and re-shedule which option will give better result on account of project progress.
Expert remarks will be highly appreciable.
With Best Regards,
Sunil.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?