Dear All,

The case scenario of the Project is like this :

After completion of gradeslab client removed the scope of the building and given to another contractor.

My question is Option A: Upto that instance can we put the remaining works of that building as 100% complete, or option B we have to revise the Baseline by removing the remaining activities of that Building and re-shedule which option will give better result on account of project progress.

Expert remarks will be highly appreciable.

With Best Regards,

Sunil.

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    It depends on what your

    It depends on what your contract says.

     

    Some contract forms have no mechanism for a change in scope to bring the contractual completion date forward, some do.

    Some contracts require a project to be re-baselined with every major contract variation,some don't.

    Read your contract and/or check with your contract manager

     

    If this is not a contractual issue, and you are talking about an internal baseline purely used to mintor project progress rather than manage the contract, then re-baselining will give you a more accurate measure of project progress.

  2. 0
    Sunil Babu ·

    Thanks Gary

    Thanks Gary

  3. 0
    SAADI karim ·

    Dear Sunil.       I thing is

    Dear Sunil.

           I thing is better to remove the remaining tasks regarding the building and get the new baseline and do analysing what you have to complete.

     

     

    Cheer

    SAADI 