Problem to make Recovery Plan as a new Baseline

Muhammad TahirMember for 14 years 3 months
Created
2
3
0

Hi Guys,

I prepare a recovery plan from last updated program, i was monitoring the progress based on total Budgeted Cost and all activities were Phisical % type. My project was in delay due to our mistake so i adjust the remaining duration by increasing the productivity and changing some logic. Now i want to use this as a new baseline so which values i have to use. Remaining total Cost or Budgeted total Cost as Planned Value?

2 replies

Oldest first
  1. 0
    nadeem Ghulam Qadir ·

    Dear Sir...Kindly tell me how

    Dear Sir...

    Kindly tell me how to calcaulte the planned %  and actual %  and time elapsed of project. with example...

    I am waitng  your positive response ..

    With Regards

    Nadeem

     

  2. 0
    Robin Clare-Talbot ·

    I would recommend using as

    I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.

    50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.

Log in or join to reply