Problem to make Recovery Plan as a new Baseline
In the Open Standard
Muhammad TahirMember for 14 years 3 months
- Created
- 2
- 3
0
Hi Guys,
I prepare a recovery plan from last updated program, i was monitoring the progress based on total Budgeted Cost and all activities were Phisical % type. My project was in delay due to our mistake so i adjust the remaining duration by increasing the productivity and changing some logic. Now i want to use this as a new baseline so which values i have to use. Remaining total Cost or Budgeted total Cost as Planned Value?