Skip to content

Strange Case of Total Float

Binas MohamedMember for 11 years 3 months
Created
2
3
0

Hi all,

 

I started this thread to discuss a avery strange case of total float i encountered..

I had prepared a microprogram for a small section of work which I had checked all links,dates and had the correct finish date as planned with a total float of 0.

Some activities were in progrss and had actuals.I exported this project and send it to the client as well.

I assigned it a baseline and started updating weekly.

 

Two weeks later,I had to add an activity to the baseline microprogram.I imported it back and when I scheduled it,it shows a negative total float of -6!!

The data date is same as before and I checked the calendar as well.

Im facing this issue for the first and can't seem to find a proper solution;any advice will be helpful

 

 

Thanks in advance

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    Check for out-of-sequence

    Check for out-of-sequence progress after making sure there are no external links, no activity date constraints, no project level finish constraint.

    Depending on your settings out-of-sequence can be identified by the activity being split with progress before DD and remaining duration some time after DD.

    Good Luck

  2. 0
    Zoltan Palffy ·

    These are few things in your

    These are few things in your post that jump out at me.

    First you say that "I have assigned it a baseline and started updating weekly". yet you say "The data date is same as before and I checked the calendar as well".

    If you are updating this weekly then the data date should change each week to reflect the date thru which progress is for that particular week.  

    Secondly you say that "Two weeks later,I had to add an activity to the baseline microprogram.I imported it back and when I scheduled it,it shows a negative total float of -6!!"

    Why would you add a new activity into the baseline and not teh current schedule. 

    Also you added an activity this could be on the critical path causing the negative float of -6. 

    .

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?