Calendar Issue
In the Open Standard
Zahid MajeedMember for 10 years 7 months
- Created
- 6
- 4
0
I am facing a problem while assigning the calendar to activities. Actual I assign a calendar of 12 hours per day working but P6 pick up 11 hours per day and in the next day working should be start at 6:00AM but it is going to start on 14:00 PM why it’s all happening I don’t know.