Calendar Issue

Zahid MajeedMember for 10 years 7 months
Created
6
4
0

I am facing a problem while assigning the calendar to activities. Actual I assign a calendar of 12 hours per day working but P6 pick up 11 hours per day and in the next day working should be start at 6:00AM but it is going to start on 14:00 PM why it’s all happening I don’t know. 

6 replies

Oldest first
  1. 0
    Azher Kalhoro ·

    Majeed,At first instance

    Majeed,

    At first instance check time in scheduling box, it looks to me that you haven't setup correctly scheduling time. 

    It should be appear 

    scheduling date + time (00:01)

    If you fix it in this order then i hope your probelm will be resolved.

     

    Thanks,

    Azher Kalhoro

  2. 0
    Rafael Davila ·

    Look for Activity 1010 FS

    Look for Activity 1010 FS relationship with lag as shown in your figure, this lag value might be part of your problems. Also remember to check what calendar is the lag calendar.

    Good Luck.

  3. 0
    Tom Boyle ·

    I would start by adjusting

    I would start by adjusting User Preferences to increase decimal places in time units/Durations format.  A1000 runs from 0600 to 1600 (10 hours) clearly not a full 1 day on a 12-hour calendar.  Chances are you changed calendars after specifying durations, so your durations may now include fractional parts of days that you cannot see.

  4. 0
    Zahid Majeed ·

    Thanx allTom Boyle u are

    Thanx all

    Tom Boyle u are correct thr is problem in decimal plave when i put one decimal then the duration will become correct as i assign in calendar. but how i can stop this problem in future that i put the no. of duration & P6 consider as it is assign in calendar.

     

    Thanks regards

    ZAHID MAJEED 

  5. 0
    Tom Boyle ·

    Hello Zahid,P6 records

    Hello Zahid,

    P6 records durations in hours.  When you enter the duration in days, P6 multiplies your entry by the hours-per-day of the activity's calendar and saves the result (in hours.)  If you later change the calendar, P6 does not automatically go back and modify the duration.  This is normal.

    Avoid "this problem" by thinking about your activity calendars (i.e. hours per day) before entering durations in days.

    Good luck, tom

  6. 0
    Tom Boyle ·

    (duplicate)

    (duplicate)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?