Does the construction materials procurement time get entered into the project plan?
In the Open Standard
Timothy ReduchaMember for 10 years 11 months
- Created
- 2
- 2
0
Hello everyone!
I am a planning neophyte, and my first thought, was wether or not i should be entering the procurement time into my schedule. In this case, i'm buiding a cinema. The procurement time i've been given for ceiling materials by the suppliers is 6 to 8 weeks.
Does this get entered into my project plan? I'm assuming it does, because that way, it will show, that the adjoining task, installation of the ceiling, is not starting late because of poor planning, but because i'm waiting for the delivery of my materials.
Thank you
2 replies
Oldest firstLog in or join to reply