Progress Update - Restatus

Mohamed YusufMember for 13 years 6 months
Created
2
2
0

Respected Engr's,

For an ongoing project, with duration completion of 4month, the Lead Consultant (A) was suddenly changed to another Consultancy (B). Now, the issues is during those 3 months, whatsoever the Engineering Submittals i.e. Prequalifications / Materials/Shop Drawings... approved by Consultant (A) is being resubmitted to Consultant (B) and new approval dates are being received.

Kindly advise, how to status the exisiting Completed activiites as well as In Progress activities, especially Engineering.

 

Kind Regards

Yusuf

2 replies

Oldest first
  1. 0
    Mohamed Yusuf ·

    Can anyone please guide me

    Can anyone please guide me for this topic......

  2. 0
    Umer Mehmood ·

    Dear YousufThis can be done

    Dear Yousuf

    This can be done by adding a new heading showing impact activities

    The first activity to be the factor causing the impact

    The next activitiees will be additional impact to be advise and show result factor causing delay 

     