Fuel Storage Tank
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 3
- 3
0
Hello All,
I would like to know the Construction activities in Tank Construction " Fuel Storage Tank - Fixed Cone" . Its a 10000 BPD Tank.
I have listed dow the activities in the sequence of Construction but please let me know if anymore details need to be added and monitored
Tank Civil Foundation
- Tank Foundation Excavation and compaction
- Blinding Concrete
- Form and Steel Work
- Concrete Pouring
- Soil Fill and Compaction
Tank Bottom
- Bottom Plates Installation
- Bottom Plate - Coating
Tank Shell
- Shell Plate Installation
- Shell - Nozzle and Manway Installation
- Shell - Final Coating
Tank Roof
- Roof - Center Deck Plate Installation
- Roof - Drainage Piping
- Roof - Final Coating
Tank Acessories and Fire Fighting
- Internal Accessories
- External Accessories
- Foam Piping Installation
- Final Coating
Can anyone let me know the manpower required to do the work.
Thanks
Jithin
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?