Skip to content

Actual Units Updation - Physical, Duration & Units % completion.

Sarthak SharmaMember for 10 years 8 months
Created
0
3
0

 

In higlighted line why my budgets units calculating from unit % completion as i selected Physical % completion and in project settings also i changed to Physical.

Kindly reply how to update i want my budgte popints calculated from physical % completion i tried all methods but no use.

i want actual budget units comes 50% as physical instead of 27% of Units % 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?