Total Float

Oguntade AdekunleMember for 9 years 10 months
Created
2
3
0

Please i do have much float whan am preparing baseline program, can any one help me? And what are the things to consider while preparing a baseline Program for best result?

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi OgutandeTighten up the

    Hi Ogutande

    Tighten up the logic by removing loose ends.

    Adjust all SS FF Links - best to use only FS logic.

    Remove all constraints.

    Best regards

    Mike T.

  2. 0
    Patrick Weaver ·

    Float is the least of your

    Float is the least of your worries - first make sure the logic, resources, and durations are accurate, reasonable and achievable. Float is simply a by-product, see: http://www.mosaicprojects.com.au/PDF/Schedule_Float.pdf