Updating Existing Project for new Baseline

Anderson CharlieMember for 10 years 5 months
Created
4
4
0

Hi,

Recently I have just amended my resources cost. I want to update my cost baseline by updating the current project by importing previous updated *.xer files. However, when I try to schedule my program it become 0% (except for the 100% activities). Can anyone advise me why does this happen? Or do I have to manually insert in the performance percentage manually one by one to each of the activities. Which by the way consist of more than 500 activities!!!

Thanks in advance guys

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    assign the baseline then

    assign the baseline then select update baseline and select costs 

  2. 0
    Amro Ahmed ·

    Please also Make sure the

    Please also Make sure the following:

    - No filter has done in the update  especially,(in progress activities)

    -in update , the option for thechnique  computing pecent comletion is custom  not 0/100

     

    Good luck

  3. 0
    Anderson Charlie ·

    Hi Mr Zolfan,Your method

    Hi Mr Zolfan,

    Your method works!! thanks for the reply.

    Anderson

  4. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 