Updating Existing Project for new Baseline
In the Open Standard
Anderson CharlieMember for 10 years 5 months
- Created
- 4
- 4
0
Hi,
Recently I have just amended my resources cost. I want to update my cost baseline by updating the current project by importing previous updated *.xer files. However, when I try to schedule my program it become 0% (except for the 100% activities). Can anyone advise me why does this happen? Or do I have to manually insert in the performance percentage manually one by one to each of the activities. Which by the way consist of more than 500 activities!!!
Thanks in advance guys
4 replies