I would like to welcome you. I found a problem during my training in Primavera P6. I have two questions that will astonish me during the work I did during my training in which I did not find an answer. Let me ask you and thank you for your understanding.
1 / - During a progress update the activities will be colored yellow until the data date. They are not all finished at 100/100, there are activities that will take 30/100 and others that have not yet started, on the other hand all activities that are colored in yellow should be completed only in Real is not the case. How I can do this to tell Primavera at Minute Satus in Activity Details to postpone what remains of the unfinished activities to another date later.
2 / - In the course of the update of the project and to bring back the actual dates of the progress of the tasks, I noticed that TAC or Original duration of the project which changes by itself against the BAC or the Budgeted Total cost Does not change?