changing the activity links and lags
In the Open Standard
Taher AbualsamenMember for 15 years 7 months
- Created
- 2
- 4
0
I m trying to review the MS schedule submitted by the Contractor, i noticed that he is changing the activity links and lags in the updated monthly schedule, does anyone have a spreadsheet or a certain method to review the links I tried exporting the links to xls but it is not easy due to the links have 2 unique IDs (Predecessor and successor)
Taher
2 replies