Duration Difference - At Completion Duration based on Default Calendar

Jithin KambhikanamMember for 15 years 6 months
Created
2
3
0

Hello Everyone,

The is a Difference in Duration in the WBS. The Project Duration is shown as 174 Days and Milestone Duration is 243 Days (which is the calendar days).

 

I have 3 Types of Calendar in the Project a). 5 Days Work Week, b). 6 Day Work Week and c). 7 Day Work Week.

The Default Calendar of the Project is 7 Days Work Week.

Could you please guide me on how to show in the Project Duration as 243 Days (Calendar Days).

 

Regards

Jithin

2 replies

Oldest first
  1. 0
    Jithin Kambhikanam ·

    HI Everyone, Got the Answer

    HI Everyone,

     

    Got the Answer after doing some research,

     

    I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week.

    Now the Total Duration is same as the the Below WBS Duration.

     

    Regards

    Jithin

  2. 0
    Zoltan Palffy ·

    just make sure that you set a

    just make sure that you set a defaul calendar for the PROJECT