Duration Difference - At Completion Duration based on Default Calendar
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 2
- 3
0
Hello Everyone,
The is a Difference in Duration in the WBS. The Project Duration is shown as 174 Days and Milestone Duration is 243 Days (which is the calendar days).
I have 3 Types of Calendar in the Project a). 5 Days Work Week, b). 6 Day Work Week and c). 7 Day Work Week.
The Default Calendar of the Project is 7 Days Work Week.
Could you please guide me on how to show in the Project Duration as 243 Days (Calendar Days).
Regards
Jithin
2 replies
Oldest firstLog in or join to reply