9days delayed

Ahmed ShoMember for 8 years 5 months
Created
5
2
0
Hello guys It's the last day of the month and I have been assigned couple of projects to update, I have updated most of it but I have 2 projects left to update. One of this projects already have 9 days delay with a terminal float duration of 6 days. Please can anyone help me of how to update this delayed projects...Thanks

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ahmed. Remove the end

    Hi Ahmed. Remove the end constraint flag and let the logic run free. Best regards Mike T.
  2. 0
    Zoltan Palffy ·

    work faster

    work faster 

  3. 0
    Ahmed Sho ·

    Thanks @Zoltan

    Thanks @Zoltan
  4. 0
    Ahmed Sho ·

    Thanks alot @Mike success

    Thanks alot @Mike success
  5. 0
    Zoltan Palffy ·

    do not remove the constraint

    do not remove the constraint at the end if it is contractual 

Log in or join to reply