HELP! Leveled Resources Delayed by Years ? WTF?
In the Open Standard
Jean-Michel AlbertMember for 11 years 6 months
- Created
- 2
- 4
0
Hello all,
I have leveled 2 resources in a simple programme.
After levelling,the commencment of their associated activities are being delayed by 2 years from the data date.
I cannot see any other incriminating features of these activities:
- there are no constraints associated with these activities where these resources are assigned
- the resource and activity calendars are aligned
- the resource levelling and scheduling settings are completely blank, i.e. there are no unusual settings turned on.
WTF ?!?