Skip to content

Performance % Complete Change After Assigning Baseline

Ahmad AbdRabouMember for 11 years 4 months
Created
2
4
0

As per the above subject, there's a difference in Performance % complete before and after I add & assigne a baseline.

that difference is not for all items, some items doesn't change.

I need to understand what happened.

2 replies

Oldest first
  1. 0
    Kyle Dundas ·

    Hi Ahmad,P6 Uses your BL to

    Hi Ahmad,

    P6 Uses your BL to Calculate Performance % Complete.

    If you go to the ADMIN TAB and ADMIN PREFERENCES this window will pop up:

    Select Earned Value Tab on the Left.

    See the bottom calculation and chose the one that best suits what you looking for.

    Either way, your perforamce % complete will change when assigning a baseiline.

    When no baseline is asigned it uses the current project to calculate Earned value.

     

    Hope this helps

     

    Kind Regards

    Kyle Dundas

  2. 0
    Ahmad AbdRabou ·

    Thanks a lot for replying, I

    Thanks a lot for replying, I appreciate that so much.

    can you explain to me why is this happening?

    I can expect one of the reasons but it's not sufficient to cover the whole thing.

    that reasone whould be that, the diference happens when the schedule have some activities that have progress but not completed. when baseline is loaded, the total progress will be calculated as if the ongoing activities are completed, and that would make a change in Perforemance % Complete, and of course it should be relative to the amount of ongoing activites and it's weight. Please, correct me if I'm wrong.

    with that being said, I still believe that there's another reason. I hope that you can help me understand it.

    Thanks again.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?