Skip to content

Impact of Global calendar vs Activity based calendar

Farhan AftabMember for 8 years 2 months
Created
3
2
0

Hi Guys,

If a programme has a default Global calendar with two days a week off ( sat/sunday), and it is ticked as default in calendars. But, the individual activities have three different calendars, 6 days a week, 7 days a week and the default one, stated above.

Which one takes precdence in scheduling? What is the difference between default calendar and then choosing separate activity based calendars?

Thanks

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    NONE take precedence its

    NONE take precedence its whatever your calendar  that the activity is assigned to. BY design when adding a new activity will automatically be assigned to the calendar listed in the defaults tab which is in the projects directory

  2. 0
    Farhan Aftab ·

    Thanks Zoltan ; Noted.

    Thanks Zoltan ; Noted.

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?