Skip to content

Programme Forecast

Debosky WaleMember for 12 years 3 months
Created
4
4
0

 I have been asked as a client-planner to produce an impact analysis in the graphical form of a delay which has been raised by contractor accepted by the client. Apparently what comes to mind is an S curve to forecast new completion date considering contractor usually submit xer file. Just want to clarify if anyone has done this before using any other method as against the aforementioned 

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Debosky The usual and

    Hi Debosky The usual and simplest way is to set the dropline to vertical and re schedule. Best regards Mike Testro
  2. 0
    Debosky Wale ·

    Hello Mike,Thank you so much

    Hello Mike,

    Thank you so much for your help.

    To be honest, I don't understand what you meant, can you please elaborate more, please ?

     

    Regards,

  3. 0
    Mike Testro ·

    Hi DeboskyWhen you add

    Hi Debosky

    When you add progress to a programme you set data date with a dropline that sets the date of the progress report.

    The drop line can be Zig Zag or straight.

    When the progress is added and the dropline is straight then the actual completion date is revealed when rescheduled

    You can set up 2 colums that shows planned completion and actual completion.

    This data can then be extracted to a spreadsheet and you can create youe s-curve.

    I trust that is clear enough.

    Best regards

    Mike Testro

  4. 0
    Zoltan Palffy ·

    an S-curve typically deals

    an S-curve typically deals with resources. I think that the client is looking for a TIA time impact analysis which meands adding the delay into the schedule and showing the activities and logic that was added to impacted the schedule in a graphical Gantt chart or time scaled logic diagram.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?