Retaining Activity ID logic
In the Open Standard
John PeaseMember for 10 years 7 months
- Created
- 3
- 4
0
I need some help please. I have two seperate schedules linked together by activity ID's, but on a monthly basis I will need to update and produce copy files and re-write the links because they are not retainied. The Project ID changes but not the Activity ID remains the same.
This is obvioulsy time consuming, and because the schedules are updated they will be individually different files. So the question is can you retain the links between schedules even if they may have different data date etc. or different copies but still retain the same activity ID logic.