What are the 'must have' Period End Reports (Non Cost / Resources loaded)
In the Open Standard
Philip JamesMember for 10 years 6 months
- Created
- 1
- 3
0
Hi
What are the must have period end reports, I would be advised to produce
Currently, I receive our contractors programme, and produce the following reports
1. Full Programme, with Last Period and Baseline Variances
2. Critical Path Layout
3. 4, and 8 week lookahead
4. Milestone Slippage
The programme submitted is not cost or resource loaded.
Regards
Philip
1 reply
Oldest firstLog in or join to reply