What are the 'must have' Period End Reports (Non Cost / Resources loaded)

Philip JamesMember for 10 years 6 months
Created
1
3
0

Hi

 

What are the must have period end reports, I would be advised to produce

Currently, I receive our contractors programme, and produce the following reports

1. Full Programme, with Last Period and Baseline Variances

2. Critical Path Layout

3. 4, and 8 week lookahead

4. Milestone Slippage

 

The programme submitted is not cost or resource loaded.

 

Regards

Philip

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    total float report and

    total float report and a schedule narrative 