Skip to content

Cumulative budgeted resources

Kali NathMember for 8 years 1 month
Created
3
2
0

Dear experts,

In a project that I am currently associated with, our client had specifically insisted on using "Non-Labour" resources to be used as a progress measurement. They had issued a weightage for each WBS (Level-1) and requested us to report the progress in form of S-curve as well % progress in each WBS wise.

Because of the approvals from several departments, we had slipped away from the schedule and hence instructed to submit the recovery schedule. while preparing recovery schedule, I have updated all completed activities with "actuals" and marked the started activities as "started" with approx %complete. "Physical" 7 "fixed duration & time" are the constraints assigned for all the activities. while preparing S-curve, I had encountered a strange error, 4 of my activities which were finished in July 2018 (actuals updated accordingly) are showing started in Oct in "Resource assignment" under "cumulative budgeted units" criteria. because of these 4 activities, my planned progress for the finish date is 95.78% instead of 100%. 

for all these 4 activities, predecessors are completed (actuals) as well.

I request you to advise me on finding out the error caused in this.

 

thank you very much in advance.

Regards,

kali

3 replies

Oldest first
  1. 0
    Melih Keskintas ·

    Resource assignment displays

    Resource assignment displays the start and finish date of the resource and it may be different than activity start and finish dates. Probably, those resources are not your primary resoruces and  they do not drive your activity dates, therefore, they may finish later  than activity finish date. You can set your resources dates manually for those activities with respect to your activity dates. 

     

    Regards,

    Melih 

  2. 0
    Melih Keskintas ·

    Resource assignment displays

    Resource assignment displays the start and finish date of the resource and it may be different than activity start and finish dates. Probably, those resources are not your primary resoruces and  they do not drive your activity dates, therefore, they may finish later  than activity finish date. You can set your resources dates manually for those activities with respect to your activity dates. 

     

    Regards,

    Melih 

  3. 0
    Zoltan Palffy ·

    are these LOe activities ?

    are these LOe activities ?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?