Hi,

I am a planning engineer working on Highways projects. At tender stage I create phasing diagrams to accompany the programme. 

I was just wondering what software people use to create their phasing plans. I have previously just used Paint or Word to overlay shapes onto site drawings but find this method quite primitive. 

Any suggestions of better methods to create a much more proffesional output?

 

Thanks,

 

Andrew 

3 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Check out Phase Manager, you

    Check out Phase Manager, you can get more info from othe Planavista site here: https://planavista.de/en/software/#phasemanager

  2. 0
    Alexandre Faulx-Briole ·

    Hi Andy,the official address

    Hi Andy,

    the official address for PhaseManager is:

    https://www.phasemanager.com/en/

    PhaseManager was designed and developped in France by ProjetLinéaire company

    Alexandre

  3. 0
    Andy Beckett ·

    Thank you

    Thank you

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?