Skip to content

Initial programme included within contact was not rescheduled before issuing

Matthew KlinefelterMember for 7 years 6 months
Created
3
3
0

Ive come across an interesting issue on a project where we have a programme included within our contract (NEC3). This programme had not been rescheduled prior to being included within the contract and as such the dates are not in line with the logic and constraints contained within the programme. Once rescheduled the dates are changed significantly.

My opinion on this is that a programme is more than the depiction of the dates and activities and should be reviewed and assess once it has been rescheduled as this is how the programme is operating in line with the logic and constraints written. The unscheduled version of the programme is in error as the dates are not working in line with the logic and constraints. Would be interested in others thoughs on this please and any case studies/additional information would be great.

Thanks in advance

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Matthew - Welcome to

    Hi Matthew - Welcome to Planning Planet.

    Just admit the mistake and submit the corrected programme.

    And while you are at it take those constraints off - they shouldn't be there.

    Best regards

    Mike Testro

  2. 0
    Zoltan Palffy ·

    Mike is correct The

    Mike is correct 

    The constrains in the schedule shoule be contractual ones. Either Contractual milestones or if you are give release dates for certain areas. ALL CONTRACTUAL

  3. 0
    Matthew Klinefelter ·

    This was a programme produced

    This was a programme produced by a contractor and written into our subcontract not something that has been submitted for acceptance. Thanks for the clarity.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?