Budgeted Manhours and Budgeted Cost

Muhammad BilalMember for 11 years 6 months
Created
1
2
0

Dear Fellows / Seniors,

I got estimates from estimation dept. after winning a tender. in which cost is calculated against manhours but the manhours were worst and was not good estimation. so i created manhours based on my experience. In short now, my manhours for each activities containing more than one Labor & Equipment resources in one activity are different. Now when i put Price/Unit in Resource Tab of Primavera, i am getting getting different result which is obvious. Now what i want is to reflect Budgeted Cost for each activity same like in the Rates we Quoted to Client using My Manhours. I tried to make a user defined column as Percentage which could multiply the Budgeted Cost to give me the required result but failed.

 

1111111111.jpg

 

I successful in Excel but dont know how to do it In Primavera P6. Formula in my Thought to get the required result:

Budgeted Units * Price/Unit * User Defined (%) = BOQ Amount.

 

How to do it? or any Other way??

 

Regards

Bilal

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    add a resource and make sure

    add a resource and make sure that calculate cost from units is NOT checked

    then add the resource for alll of your activities then exort the resource and budget units and cost to excel

    populate manhours and costs in excel

    at the project level go to Projects and make sure that your project is open and highlighted

    then on the resources tab make sure that under resource assignments that resources can be assigned to the same activity more than once is NOT checked 

    then import the excel sheet back into P6

Log in or join to reply