EV and PV using cost and hours
In the Open Standard
Abderrahim OUBDIMember for 6 years 8 months
- Created
- 2
- 4
0
Hello,
I noticed that primavera P6, calculate EV and PV only from cost value, what if we want to calculate EV and PV from labour units.
Imagine if we have ressource loaded a schedule with hours and cost, how can we obtain the EV and PV in different point of views cost and hours separetely