EV and PV using cost and hours

Abderrahim OUBDIMember for 6 years 8 months
Created
2
4
0

Hello,

I noticed that primavera P6, calculate EV and PV only from cost value, what if we want to calculate EV and PV from labour units.

Imagine if we have ressource loaded a schedule with hours and cost, how can we obtain the EV and PV in different point of views cost and hours separetely

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Just go to columns and add a

    Just go to columns and add a column it is under earned value its called Earned Value Labor Units

  2. 0
    Abderrahim OUBDI ·

    Primavera can calculate EV

    Primavera can calculate EV and PV only for each activitiy if it is loaded in hours (labor units) but he cannot give the EV or PV in the WBS summary of the activities unless you assign the PRICE/UNIT equals to 1.

Log in or join to reply