Creating deliverable milestones within a work activity....explained below.
- Created
- 0
- 3
I have an activity of work which has a defined begining date and duration. For this work there are several deliverable document items. I have set these as start miletones and related to the work activity with a start to start relationshbip. The documents themselves don't alweays have successors but I don't want to leave an open end and thought i would coule make a Finish to Finish activity with the work activity. However P6 not letting me do that. I have never come accross this and not sure how to deal with it. i do need to show the deliverables as activities with milestone dates to track progress and of course some do have significant successor ties but not all.
any guidance / suggestions appreciated.
work activity (5 weeks)
SS deliverable milestone A
SS deliverable milestone B
SS Deliverable milestone C
a,b, and c need to be completed before the work activity can end.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?