Hi everybody,

I would like to apply a Global Change on my schedule, automatically, on a regular basis.

The best solution would be to have something possible with the Job Services, but we know that the option is not possible.

Does anyone have an idea to run a GC automatically?

Regards

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you could do it with the APi

    you could do it with the APi interface 

  2. 0
    Frederic Fasquelle ·

    Sorry, but I don't know what

    Sorry, but I don't know what is an API interface. Can you explain more?

  3. 0
    Zoltan Palffy ·

    The Primavera Integration API

    The Primavera Integration API is a Java-based API and server that enables developers to create client code that can seamlessly access Primavera’s project management functionality

     

    https://docs.oracle.com/cd/E17784_01/Technical_Documentation/Integration_API/setup.pdf