Engineering Submittals!
In the Open Standard
Rami Al HaddadMember for 21 years 4 months
- Created
- 7
- 2
0
Hi All,
I think many of you must face this issue preparing and updating your schedules, the issue with engineering submittals and approvals.
My question is! what is the best way to update such activities assuming that for each submittal we have one submit activity and one review and approve activity.
i have encountered 2 methods:
1) to consider the submittal as not even done until it has already been approved and hence use the actual for the approved submittal to update the activities.
2) to update it and give it a % complete depending on the the review cycle!
i find the first more logical! I just wanna hear from you! which is better! what other ways are there! which stands stronger in claim/delay analysis and arbitration.
Thank you!
I think many of you must face this issue preparing and updating your schedules, the issue with engineering submittals and approvals.
My question is! what is the best way to update such activities assuming that for each submittal we have one submit activity and one review and approve activity.
i have encountered 2 methods:
1) to consider the submittal as not even done until it has already been approved and hence use the actual for the approved submittal to update the activities.
2) to update it and give it a % complete depending on the the review cycle!
i find the first more logical! I just wanna hear from you! which is better! what other ways are there! which stands stronger in claim/delay analysis and arbitration.
Thank you!
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?