progress vs completion date
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 2
- 4
0
Hi Planners,
I am preparing S-Curve for construction project, let's assume the planned progress for the month is 60% and the actual progress is 55%, we are 5% behind. It is not necessary mean that the planned completion date has shifted or should go further?
I think it is not necessary the planned completion date to go further, am I right?
I seriously need your explanation
Regards,
Muataz
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?