Level of Effort (LOE) - Activity Type
In the Open Standard
Suhaila TsuMember for 15 years 4 months
- Created
- 5
- 2
0
Dear Experts
For activity type - Level of Effort - why i can't assign duration to it. Every time i hit F9, the duration will go back to Zero.
By the way, i have not assign any baseline. I was just developing my work programme.
I have tried using the Sucessor FF , but if i use that , the duration would be too long.
FYI, i was assigning Activity name: Performance Bond as LOE.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
