Level of Effort (LOE) - Activity Type

Suhaila TsuMember for 15 years 4 months
Created
5
2
0

Dear Experts

For activity type - Level of Effort - why i can't assign duration to it. Every time i hit F9, the duration will go back to Zero.

By the way, i have not assign any baseline. I was just developing my work programme. 

I have tried using the Sucessor FF , but if i use that , the duration would be too long.

FYI, i was assigning  Activity name: Performance Bond as LOE. 

 

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Suhaila,Level of Effort

    Hi Suhaila,

    Level of Effort (LOE) or Hammock activity is driven by activity relationship. The start of activity should be link to Activity where it needs to start using (SS) Start to Start predecessor and finish is link to Activity where it needs to finish using (FF) Finish to Finish Successor. See sample below:LOE-Sample

    LOE activity does not have duration on its own.

  2. 0
    Zoltan Palffy ·

    you are missing the whole

    you are missing the whole point of a LOE

    a LOE has a predcesso with a SS and a successor with a a ff and it AUTOMATICALLY calulates the duration betweeen the predcessor start date and the successors finish date. 

    If you you do not want his then change the activity type.

  3. 0
    Suhaila Tsu ·

    Alright. Thank u Zoltan Paffy

    Alright. Thank u Zoltan Paffy

  4. 0
    Suhaila Tsu ·

    Ok. Thank u Rodel Marasigan

     

    Ok. Thank u Rodel Marasigan

  5. 0
    Rodel Marasigan ·

    yw happy to help

    yw happy to help