Industry norm? if progress is through December you call the your Dec. Update, not Jan correct?
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 3
- 3
0
Industry norm? if progress is through December you call the your Dec. Update, not Jan correct? That is the way I have always seen it, and it is best to use Jan 01 as the data date correct? - that way you get all of Dec. - that is better than messing with time - P6 naturally defaults to the AM for the data date correct, why mess with it just use Jan 01 right?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
