Non Labor Units Changes
In the Open Standard
Siddiq AhmedMember for 11 years 6 months
- Created
- 2
- 3
0
Dear Members,
I am updating my project,on a specific activity i have non labor unit assigned 30h when i am progressing the activity to 80% i am updating my actual units to 24h and remaining to 6h but when i run the schedule after updating the units it is going back to previous progress of 25%. Kindly help me to troubleshoot this problem.