Non Labor Units Changes

Siddiq AhmedMember for 11 years 6 months
Created
2
3
0
Dear Members, I am updating my project,on a specific activity i have non labor unit assigned 30h when i am progressing the activity to 80% i am updating my actual units to 24h and remaining to 6h but when i run the schedule after updating the units it is going back to previous progress of 25%. Kindly help me to troubleshoot this problem.

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Siddiq,It seems that the

    Hi Siddiq,

    It seems that the Calculation Settings on your resource assignment is link to duration %.

    1) Goto Project module or click the folder icon (Project) on the left of your screen.

    2) Click the project that you are updating (you will see that the folder icon for this project is open)

    3) Select or click the Calculation Tab

    4) Under the Resource Assigments (right side of the tab) Untick the box with "Recalculate Actual Units and Cost when duration % complete changes.

    5) Then go back to Activity module and change the actual unit then re-calculate (F9). Check if the Actual units still changing after re-calculate or run schedule.

    I hope this solve your problem.

  2. 0
    Siddiq Ahmed ·

    Thanks, This method solved

    Thanks, This method solved the issue.