I've multiple crews working on the same activity type, but diferent buildings.

Assume the are steel fixers and the overall productivity is 100kg/day for today, and by simple analysis, I found that 50% of crews (Group A) produced 150kg/day and the other 50% of the crews (Group B) produced 50kg/day.

Is it correct to say that Group B reduced the overall productivity by 30% ?

What is the mathematical bases for such calculation? because I want to expand the analysis.

Thanks,

Ahmad.

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    Activity duration is a

    • Activity duration is a function of assigned resources and their production rates.
    • Individual resource productivity is not the same as team productivity. The production rate for a crew of 2 steel fixers is usually twice the production rate for a crew of 1 steel fixer but it can be other factor.
    • The production average production rate is a function of crew production rate, crew assgment and crew work hours.
    • If using Spider Project we can assign production rate at the activity level or at individual resources. Spider Project Production Type activityes, Multiresources as a Skill and resource leveling will automatically select best available crew and adjust activity durations per crew production rate.

    2022-06-12-13-21-25-Activity-Gantt-Team-Productivity-01-1-Team-Productivity-01 hoover the thumbnail and click for a better view.

    Good Luck.

  2. 0
    Rafael Davila ·

    (No subject)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?